Friday 28 June 2013

Rainy days

June in the Okanagan valley was very wet and July started the same.  All that water slowed down the build by a couple of weeks.

I have only received part of my order for metal, Spartan Metal was backed up with too much work but I didn't need the rest of the order anyway.  During the week I went over the design and decided to add 3 more out riggers per side.  This dropped the load on each on to 230lbs.  I also realized a was missing a cross bar.  I think I changed my order about 4 times but Joel was patient with me.  The rest of my order was finished today, I quickly ducked out of work to pick it up.

Expenses to date $3,928